Skip to content

Milwaukee Shifts $1.6M From Police Vehicles to Fire Apparatus, Leaving $400,000 for Police Vehicles

The fire department had asked for $26.8 million for major equipment; 20 of the city’s 43 fire engines are more than 15 years old, and the city’s public works department expects no improvement in 12- to 18-month lead times for customized heavy equipment.

A Milwaukee Fire Department engine with hose lines attached and an aerial ladder truck at a fire scene on a downtown Milwaukee street at dawn
Milwaukee Fire Department engine and aerial ladder companies at a fire scene downtown. Image Credit: Milwaukee Fire Department

The Milwaukee Fire Department will get $1.6 million in new borrowing for major capital equipment in 2027, enough to fund one new fire engine, CBS 58 reported. The department had asked for $26.8 million for major capital equipment, and the mayor’s proposed budget provided none, according to the Legislative Reference Bureau (LRB). The money comes out of police vehicles, cutting that line from $2 million to $400,000.

Mayor Cavalier Johnson signed the budget Nov. 17 without vetoing any of the Common Council’s changes, the Milwaukee Journal Sentinel reported.

Where the Police Vehicle Money Stands

The mayor’s proposed budget carried $2 million for police vehicles within a $4.1 million capital appropriation for facilities maintenance and the purchase of 30 new police vehicles, the LRB’s police budget review shows. The council’s change reduces new borrowing for police vehicles by $1.6 million, leaving $400,000, according to the meeting minutes. The record does not say how many of the 30 vehicles will still be bought.

The city had 68 hybrid police interceptors in the fleet as of September 2026, with 62 more undergoing upfitting before being placed into service and 130 anticipated by December 2027, according to the LRB’s review of Department of Public Works (DPW) Fleet Services. Police equipment had a 92% in-service rate so far in 2026, and the planned rate for 2027 is 85%, the same as for light and heavy equipment. “When new vehicles are not funded or are not available in a timely manner, the fleet ages and needs more repairs. This results in a lower in-service rate,” the review says.

An Aging Fire Fleet

The department identified more than $60 million in capital needs for equipment and facilities, CBS 58 reported. A council proposal to add $3.2 million more in new borrowing for fire equipment failed. “There will be a reckoning day when our equipment no longer can serve its purpose,” said Ald. Peter Burgelis, who also pointed to an incident in which a wheel fell off a fire engine, CBS 58 reported.

The National Fire Protection Association (NFPA) recommends frontline engines and trucks be under 15 years old and reserve units under 20, the LRB’s fire budget review notes. Its chart counts 11 frontline engines, two frontline trucks and one med unit at or past 15 years, and nine reserve engines, six reserve trucks and one med unit at or past 20. CBS 58, citing department figures, reported that 20 of Milwaukee’s 43 fire engines are more than 15 years old.

The department’s own budget presentation to the council’s Finance & Personnel Committee on Oct. 12 listed “Apparatus Age & Condition Remains a Concern” among its major updates. As of that date, two ladder trucks ordered in June 2025 were due in the first quarter of 2027, and six med units were due by the end of 2026. Request-for-proposal scoring was under way for three ladders and three engines from the $10 million 2026 capital allocation, with delivery estimated two to three years after the contract is signed. The presentation also listed an open question for the department’s repair shop: “Repair shop lease extension vs purchase/build.”

Public Works Lead Times

Lead times for customized heavy equipment such as salt trucks and garbage packers are generally 12 to 18 months, and light-duty vehicles take six to 12 months from order to delivery, the DPW review says. “The department does not expect any improvement in this area,” it says. DPW is moving away from highly customized orders toward configurations that are more readily available in the market.

The proposed budget gave DPW $10 million in capital funding for major equipment, the same as in 2026. The council also moved $350,000 within DPW’s capital budget, from DPW-Infrastructure equipment to Public Works Major Capital Equipment, to pay for Electrical Services fleet vehicles. It is a shift, not new money.

The Sightline

Public fleet intel, delivered

The stories, data, and best practices that matter, straight to your inbox. No fluff. No spam. Just the good stuff.

By signing up, you agree to receive communications from Modern Public Fleet and its trusted partners. See our Privacy Policy. Unsubscribe any time.