Hillsborough Moves Its Public Works Fleet Out of the Floodplain After Chantal Totaled Over 20 Vehicles

The North Carolina town opened its $4 million facility with covered parking for oversized vehicles. This comes 16 months after flooding at its old yard cost it one-third of its public works vehicles and equipment.

Town of Hillsborough public works trucks parked under the covered parking at the new public works facility
Town public works trucks under the covered parking at Hillsborough’s new public works facility, Nov. 20, 2026. Image Credit: Town of Hillsborough

The Town of Hillsborough, North Carolina, has moved its Public Works Division and its vehicles out of the Eno River floodplain, 16 months after Tropical Storm Chantal flooded the division’s old yard and totaled more than 20 town vehicles.

Mayor Mark Bell cut the ribbon Nov. 20 on the expanded Highway 86 North Facility, which Public Works now shares with Fleet Maintenance Operations and the Safety and Risk Management Office. Construction cost about $4 million, the town said.

“Now all of our vital equipment for our daily services are here,” Assistant Town Manager Matt Efird told CBS17. “They’re safe. They’re covered.”

What the Storm Took

Chantal dropped an estimated 10.5 inches of rain on Hillsborough overnight July 6, 2025. The town’s public works yard straddles the Eno River’s 100- and 500-year floodplains. “A total of 22 vehicles and pieces of heavy equipment were flooded,” the town reported, including two trash trucks, three dump trucks, both of its brush trucks and its only bucket truck.

Town garbage trucks, pickups and a dump truck standing in brown floodwater at the Hillsborough public works yard
Town trucks in floodwater at Hillsborough’s old public works yard after Tropical Storm Chantal in July 2025. Image Credit: Town of Hillsborough

Before expected flooding, Public Works normally moves vehicles out of the yard’s low areas. The forecast called for 3 inches of rain, which “would not have posed a threat to the town’s vehicles,” the town said. “The rapid rise of floodwaters made it impossible to move the vehicles when staff returned early Monday morning.”

The three-person fleet maintenance team towed vehicles to its shop and drained water and oil from engines, transmissions, differentials and hydraulics. Six damaged vehicles were temporarily repaired and returned to crews, but they later developed new problems tied to the flooding, including computer and electrical issues and mold, the town said.

Replacing the Fleet

On July 16, 2025, the Board of Commissioners approved a plan to replace the flood-damaged vehicles over two fiscal years, at an estimated cost of $2.3 million, using existing vehicle replacement funds, budgeted money and additional appropriations from the town’s fund balance. Any insurance payouts go back to the fund balance. In the meantime, Durham County loaned the town a brush truck through a mutual aid request, and another was rented from Florida, according to the meeting packet.

By September, the town had replaced over 20 vehicles totaled by the storm at a cost of nearly $2 million, it said in a one-year review. The flood cost the town one-third of its public works vehicles and equipment and the division’s office space. The town has spent about $2.5 million of its General Fund savings on storm recovery and recovered $2 million from its insurer and FEMA’s public assistance program.

What the New Facility Includes

Town leaders had been working to move Public Works out of the floodplain since at least 2016, and other financial needs delayed the project. Design started before the storm, and construction began in June 2025. Public Works operated from a rented unit on Cornerstone Drive in the meantime. The renovation and expansion include:

  • Covered parking for oversized town vehicles, which the town says reduces wear on them.
  • An additional vehicle bay for Fleet Maintenance Operations, with improved climate control in the workshop and sound-blocking closets for the pressure washer and air compressor.
  • Increased oil storage, secured tire storage and an improved wash bay.
  • Climate-controlled workspace for Public Works to assemble equipment and signs, plus renovated offices and storage areas.
  • A shower, kitchenette, lockers and generator power for staff working on site during severe weather.

The first bid opening drew only two of the three bids required for formal projects, so the town rebid the work. H.M. Kern Corp. was the low bidder on the second round, at $3.7 million with a $5,000 add-alternate for galvanized steel at the wash bay platform, according to a February 2025 board item. A project ordinance approved in June 2023 set the project at $4.8 million. The facility is nearing completion.

Add to Google

The Sightline

Public fleet intel, delivered

The stories, data, and best practices that matter, straight to your inbox. No fluff. No spam. Just the good stuff.

By signing up, you agree to receive communications from Modern Public Fleet and its trusted partners. See our Privacy Policy. Unsubscribe any time.