Miami-Dade Opens $245.8M Electric Bus Garage for 100 New Flyer Articulated Buses
The South Dade Transit Operations Center, the county’s first new bus garage in 40 years, begins operations Nov. 23 after a 126-day construction extension.
Source: Miami-Dade County ↗
Miami-Dade County will cut the ribbon Nov. 18 on the South Dade Transit Operations Center in Homestead, Florida, a $245.8 million garage built to store, charge and maintain 100 articulated battery-electric buses. The county’s Department of Transportation and Public Works (DTPW) expects the center to begin operations Nov. 23.
It is the first major operations and garage facility DTPW has built in 40 years, according to the county’s media advisory, which calls it the first facility of its kind in the United States. The county says the center will support more than 270 new jobs.
Built Around an Electric Fleet
The 218,000-square-foot facility at 12805 Biscayne Drive brings bus storage, charging, maintenance and operations together in one place. Its charging infrastructure can support overnight charging for up to 100 battery-electric buses, with coordinated utility connections and electrical redundancy systems, according to a November county memo. The site also has solar components, a reclaimed water system and more than 45 species of native trees, plants and wildflowers.
The buses are New Flyer Xcelsior CHARGE NG 60-foot models. Miami-Dade ordered 100 of them in 2023, along with two on-route Heliox 450-kilowatt chargers and 50 Heliox Flex 180-kilowatt depot power cabinets, New Flyer announced at the time. The buses carry 763-kilowatt-hour batteries, and 60 were slated for the 20-mile South Dade TransitWay bus rapid transit corridor. New Flyer has already delivered the buses, according to the county’s project page.
Why a New Garage
DTPW built the center because its Coral Way facility, about 30 miles away, had reached capacity, and no other county facility had the infrastructure to support that many electric buses, according to a change order memo to the Board of County Commissioners.
The board awarded the construction contract to NV2A Dragados JV in April 2024 for $245,750,156.80. A notice to proceed was issued June 10, 2024, with substantial completion set for May 14, 2026. The board later approved a 126-day, no-cost time extension, moving final completion from July 2026 to November 2026. The memo cites building and fire department code updates to the roof and fire protection systems, and changes to the emergency generator pad to meet the backup power needs of the all-electric fleet.